22-06: Hidden Oaks Street Reconstruction

Project Update - 8/12/2022

22-06: Hidden Oaks Area Street Reconstruction

The project consists of two phases, which can be seen on the project phasing map below.

 Phase 1

Construction activities during the week of August 15 will include:

  • Street grading
  • Installation of the first lift of bituminous pavement (scheduled for August 18 and 19)
  • Boulevard grading

 Phase 2

Construction activities during the week of August 15 will include:

  • Removal of any remaining existing concrete curb and gutter
  • Partial driveway removals (typically 10 to 15 feet from behind back of curb)
  • Street grading

If you have any questions regarding the project, please contact WSB inspector Sam Gonsior at 651-380-3272 or sgonsior@wsbeng.com

22-06 Phasing Map

Project Location

Hidden Oaks neighborhood including:

  • 97th Avenue from Hamline Avenue to Yalta Street
  • 97th Lane from Hamline Avenue to Xebec Street
  • 97th Court from West cul-de-sac to Hamline Avenue
  • 98th Avenue from Hamline Avenue to Xebec Street
  • 98th Lane from Wake Street to Yalta Street
  • 99th Avenue from Wake Street to Xebec Street
  • 99th Lane from Xebec Street to Austin Street
  • Hamline Avenue from Edgewood Road to North cul-de-sac
  • Wake Street from 98th Avenue to 99th Avenue
  • Wake Court from 99th Avenue to North cul-de-sac
  • Xebec Street from Edgewood Road to 99th Lane
  • Yalta Street from 97th Avenue to 99th Lane

Project Description

This proposed project area would be reconstructed with new curb and gutter, aggregate base, and bituminous pavement. The scope of storm sewer improvements is limited to adding inlets at low points where there is currently limited inlet capacity and the replacement of inlet and manhole castings. Water improvements include replacement of select gate valves, select curb stops, and adjustment of other surface features. Sanitary sewer improvements are limited to replacement of manhole castings.