18-18: Clover Leaf Parkway Area Reconstructions

Project Update - 7/8/2020

The contractor is currently working on Part 1 of the project (99th Avenue to Monroe Street). All underground utility work and pavement and curb removals have been completed. Curb and gutter was installed the week of July 6. Paving of the first lift of bituminous pavement is tentatively scheduled for the week of July 13.

Part 2 of the project (Monroe Street to Polk Street) is anticipated to begin in late July.

Project Description​


Phase 1 of the project consisted of reconstructing 93rd Lane from Trunk Highway 65 to Isanti Street, Clover Leaf Parkway from Highway 65 to Polk Street and Lincoln Street and Ulysses Street in Aquatore Park. Phase 1 was completed in the fall of 2019.

Phase 2 of the project will  occur in the spring and summer of 2020 and will consist of reconstructing Clover Leaf Parkway from Polk Street to 99th Avenue

The general construction process is as follows:

  • The existing pavement surface will be ground up into gravel.
  • Underground storm sewer utility work will be constructed where planned.
  • The gavel road base will be graded and shaped and concrete curb and gutter will be removed and replaced where concrete curb and gutter already exists (Clover Leaf Parkway NE and 93rd Lane NE from Highway 65 to Baltimore Street NE).
  • After the concrete curb and gutter has cured, the first layer (base course) of the new bituminous street surface will be paved.
  • The second layer (wear course) of the bituminous pavement will be paved.
It is the goal of the project to keep access available at all times for those residents and businesses that take direct access off of the project streets but the road surface will be gravel during most of the project.  93rd Lane NE from Highway 65 to Baltimore Street will require a complete closure to traffic for approximately three weeks so crews can safely construct the road and install the concrete curb and medians.  There may be short term delays for access to or from your driveway or on the road where you may have to wait for the construction equipment to pass by. Detours for the road closure will be marked and please follow the instructions of any flag person that may be present.

Project Location

 

The proposed project will reconstruct Clover Leaf Parkway from 99th Avenue NE to Trunk Highway 65, 93rd Avenue NE from Trunk Highway 65 to Isanti Street NE and Lincoln Street NE and Ulysses Street NE within Aquatore Park.

Project Documents

close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel
close carousel

Project Description 


Project Description 


18-18 Location Map