23-08: Southeast Area Street Reconstruction

Project Update - 6/2/2023

The project consists of four project areas, which can be seen on the project phasing map below. Project newsletters were mailed out on Friday, May 19.

Project Area 1

Construction is anticipated to begin the week of July 24. 

Project Area 2

Construction is anticipated to begin the week of June 12.

Project Area 3

Construction is anticipated to begin the week of June 12.

Project Area 4

Construction is anticipated to begin the week of June 12.

23-08 Project Phasing Map

Project Location

Southeast Area including:

  • Project Area 1:
      • 97th Lane from Austin Street to Lexington Avenue
      • 98th Avenue from Austin Street to Cord Street
      • 98th Lane from Austin Street to Cord Street
      • 99th Avenue from Austin Street to Lexington Avenue
      • Austin Street from Edgewood Road to 97th Lane
      • Austin Street from 98th Avenue to Lexington Avenue
      • Cord Street from 98th Avenue to Austin Street
      • Edgewood Road cul-de-sac (4023-4083)
      • Edgewood Road cul-de-sac (4103-4163)
  • Project Area 2:

      • West 35W Service Drive from West 35W Service Drive to cul-de-sac
  • Project Area 3:

      • Edison Street from 85th Avenue to cul-de-sac
  • Project Area 4:

      • 89th Lane from Yancy Street to 90th Lane
      • 89th Court from 90th Lane to cul-de-sac
      • 90th Lane from Zumbrota Street to Rice Creek Parkway
      • Bataan Street from 90th Lane to 91st Avenue
      • Yancy Street from Rice Creek Parkway to 89th Lane
      • Zumbrota Street from 89th Lane to 91st Avenue
      • Bataan Court from 89th Lane to cul-de-sac
      • Zumbrota Circle from Zumbrota Street to cul-de-sac

Project Description

Proposed improvements in Project Area 1 will generally involve reconstructing the existing road by removing the existing pavement and curb and gutter and installing new pavement and curb and gutter. In addition, storm sewer improvements and minor water main work will occur in certain areas.

Proposed improvements in Project Area 2 will generally involve reconstructing the existing road by removing the existing pavement and installing new pavement. In addition, storm sewer improvements will occur in certain areas.

Proposed improvements in Project Areas 3 & 4 will generally involve reconstructing the existing road by removing the existing pavement and installing new pavement. Spot replacement of damaged curb and gutter will also occur. In addition, storm sewer improvements and minor water main work will occur in certain areas.

Project Documents