24-06: 2024 Pleasure Creek Area Street Reconstruction

Project Update - 12/19/2023

The 2024 Pleasure Creek Area Street Reconstruction feasibility report was accepted by Blaine City Council at the December 18, 2024 City Council meeting with Resolution 23-177.

24-06 Project Area Map

Project Location

Pleasure Creek Area including:

  • Project Area 1
      • Territorial Road from University Avenue to Jefferson Street
  • Project Area 2

      • 99th Lane from Washington Street to Madison Street
      • 100th Court from Pleasure Creek Parkway to 360’ west towards cul-de-sac
      • 100th Court from Pleasure Creek Parkway to west cul-de-sac
      • 101st Avenue from Pleasure Creek Parkway to Jackson Street
      • 101st Court from Pleasure Creek Parkway to west cul-de-sac
      • Clover Leaf Parkway from 99th Avenue to Pleasure Creek Parkway
      • Madison Street from 99th Lane to Pleasure Creek Parkway
      • Pleasure Creek Parkway from 101st Avenue to north dead end
      • Pleasure Creek Parkway from Clover Leaf Parkway to 101st Avenue
      • Pleasure Creek Parkway from Madison Street east to south dead end
      • Pleasure Creek Parkway from President Drive to Clover Leaf Parkway
      • Pleasure Creek Parkway from President Drive to Madison Street
      • President Drive from Pleasure Creek Parkway to Territorial Road
      • Terrace Court from Pleasure Creek Parkway to south cul-de-sac
      • Washington Court from Pleasure Creek Parkway to cul-de-sac
      • Washington Street from 99th Lane to Pleasure Creek Parkway

Project Description

Proposed improvements in Project Area 1 will generally involve reconstructing the existing road by removing the existing pavement and installing new pavement and concrete curb and gutter. In addition, storm sewer improvements and minor water main work will occur in certain areas.

Proposed improvements in Project Area 2 will generally involve reconstructing the existing road by removing the existing pavement and installing new pavement. Spot replacement of damaged concrete curb and gutter will also occur. In addition, storm sewer improvements and minor water main work will occur in certain areas.

Project Documents