BlaineMN.gov - Construction Update

Welcome to the Blaine Construction Update

The construction update is published during the construction season and includes details about current road construction projects happening in the City of Blaine. You can subscribe to email notifications by visiting the notify me page and selecting Blaine Construction Update.


22-04: 2022 Street Reconstructions


Location

Project Area 1: (123rd Avenue / Buchanan Area)

  • 123rd Avenue from Buchanan Street to Ulysses Street
  • 124th Court from West cul-de-sac to Buchanan Street
  • 124th Court from Pierce Street to Buchanan Street
  • Pierce Street from West cul-de-sac to Pierce Street
  • 124th Lane from 123rd Avenue to 124th Lane
  • Pierce Court from Pierce Street to east cul-de-sac
  • Buchanan Street from Paul Parkway to 124th Lane

Project Area 2: (127th Avenue / Buchanan Area)

  • 126th Avenue from Polk Street to Taylor Street
  • 126th Lane from Taylor Street to Buchanan Street
  • 127th Avenue from Taylor Street to Buchanan Street
  • 127th Lane from Taylor Street to Central Avenue
  • Polk Street from 125th Avenue to 126th Avenue
  • Taylor Street from 126th Avenue to 129th Avenue
  • Buchanan Street from 126th Avenue to 127th Lane

Project Area 3: (129th Avenue)

  • 129th Avenue from 180 feet West of Isanti Street to Radisson Road

Project Status as of 6/9/2023

The project consists of three separate project areas, which can be seen on the 22-04 Project Area Map.

Project Area 1

Construction completed in 2022.

Project Area 2

Street construction was completed in 2022. Punch list items remain and will be completed by mid-June 2023.

Project Area 3

Street construction was completed in 2022. Final restoration, pavement striping, and punch list items remain and will be completed by the end of June 2023.

If you have any questions regarding the project, please contact SEH inspector Erik Navratil at 612-257-4184 or enavratil@sehinc.com.

For additional project information, visit BlaineMN.gov/22-04.


22-05: 89th Avenue and Davenport Area Street Reconstructions

Location

  • Baltimore Street from 85th Avenue to 89th Avenue
  • Davenport Street from 85th Avenue to 89th Avenue
  • 89th Avenue from Central Avenue (MN-65) to Davenport Street
  • 87th Avenue from Central Avenue (MN-65) to Hastings Street
  • Eldorado Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 87th Avenue to northerly dead end
  • Jenkins Court from 85th Avenue to the cul de sac

Project Status as of 6/9/2023

The project consists of five phases which can be seen on the project phasing map. Phase 1 was completed in 2022, with phases 2-5 being constructed in 2023.

Phase 1

Construction completed in 2022.

Phase 2

Construction activities during the week of June 12 will include:

  • Boulevard grading and restoration

Phase 3

Construction during the week of June 12 will include:

  • Boulevard restoration

Phases 4-5

Construction during the week of June 12 will include:

  • Utility installation

If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com.

For more information, visit BlaineMN.gov/22-05.




  • Arial
  • Georgia
  • Impact
  • Tahoma
  • Times New Roman
  • Verdana
  • 8
  • 9
  • 10
  • 11
  • 12
  • 14
  • 18
  • 24
  • 30
  • 36
  • 48
  • 60
  • 72
  • 96
  • Align Left
  • Align Center
  • Align Right
  • Align Justify
  • Default
  • Lower Alpha
  • Lower Greek
  • Lower Roman
  • Upper Alpha
  • Upper Roman
  • Default
  • Circle
  • Disc
  • Square
  • Normal

  • Headline

  • Subhead 1

  • Subhead 2

  • Hyperlink
  • Spanish
  • Chinese
  • Tagalog
  • Vietnamese
  • French
  • Korean
  • German
  • Arabic
  • Russian
  • Italian
  • Portuguese
  • Hindi
  • Polish
  • Japanese
  • Urdu
  • Persian
  • Gujarati
  • Greek
  • Bengali
  • Panjabi
  • Telugu
  • Armenian
  • Hebrew
  • Hmong
  • Haitian Creole

23-06: Northwest Area Street Reconstruction

Location

Project Area 1

  • 127th Avenue from cul-de-sac to Polk Street
  • 127th Lane from Monroe Street to Polk Street
  • 128th Avenue from Taylor Street to Polk Street
  • 129th Lane from 175 feet west of Tyler Street to Polk Street
  • Tyler Street from 127th Lane to 129th Lane
  • Polk Street from 126th Avenue to cul-de-sac

Project Area 2

  • 131st Avenue (E) from Van Buren Street to Taylor Street

Project Area 3

  • 131st Avenue (W) from Jefferson Street to Van Buren Street

Project Status as of 6/9/2023

The project consists of two phases, which can be seen on the project phasing map. 

Phase 1

Construction during the week of June 12 will include:

  • Removals
  • Gate valve replacements
  • Storm sewer installation

Phase 2

Construction is anticipated to begin the week of June 19.

For more information, visit BlaineMN.gov/23-06.



23-07: Southwest Area Street Reconstruction

Location

Project Area 1

  • 90th Avenue (from Polk Street to cul-de-sac)
  • 90th Lane (from Polk Street to Fillmore Street)
  • 91st Avenue (from Polk Street to Pierce Street)
  • Taylor Street (from 90th Lane to 91st Avenue)
  • Fillmore Street (from 90th Lane to 91st Avenue)
  • Pierce Street (from 89th Avenue to 91st Avenue)

Project Area 2

  • 3rd Street (from 90th Avenue to 90th Lane)
  • 6th Street (from 90th Avenue to 90th Lane)
  • 90th Avenue (from 3rd Street to 6th Street)
  • 90th Lane (from University Avenue to 7th Street)

Project Area 3

  • 92nd Avenue (from University Avenue to 3rd Street)
  • 92nd Lane (from University Avenue to 3rd Street)
  • 3rd Street (from cul-de-sac to 92nd Lane)

Project Status as of 6/9/2023

The project consists of four phases, which can be seen on project phasing map. 

Phase 1A

Construction activities during the week of June 12 will include:

  • Boulevard grading and restoration

Phase 1B

Construction is anticipated to begin the week of June 12 and will include:

  • Reclaiming the existing bituminous pavement
  • Partial driveway removals (typically 10-15 feet from behind back of curb)
  • Gate valve and hydrant replacements
  • Storm sewer installation
  • Street grading

Phase 2

Construction activities during the week of June 12 will include:

  • Installation of the first lift of bituminous pavement
  • Boulevard grading and restoration

Phase 3

Construction activities during the week of June 12 will include:

  • Installation of the first lift of bituminous pavement
  • Boulevard grading and restoration

If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or Travis.Pearl@bolton-menk.com.

For more information, visit BlaineMN.gov/23-07.



23-08: Southeast Area Street Reconstruction

Location

Project Area 1

  • 97th Lane from Austin Street to Lexington Avenue
  • 98th Avenue from Austin Street to Cord Street
  • 98th Lane from Austin Street to Cord Street
  • 99th Avenue from Austin Street to Lexington Avenue
  • Austin Street from Edgewood Road to 97th Lane
  • Austin Street from 98th Avenue to Lexington Avenue
  • Cord Street from 98th Avenue to Austin Street
  • Edgewood Road cul-de-sac (4023-4083)
  • Edgewood Road cul-de-sac (4103-4163)

Project Area 2

  • West 35W Service Drive from West 35W Service Drive to cul-de-sac

Project Area 3

  • Edison Street from 85th Avenue to cul-de-sac

Project Area 4

  • 89th Lane from Yancy Street to 90th Lane
  • 89th Court from 90th Lane to cul-de-sac
  • 90th Lane from Zumbrota Street to Rice Creek Parkway
  • Bataan Street from 90th Lane to 91st Avenue
  • Yancy Street from Rice Creek Parkway to 89th Lane
  • Zumbrota Street from 89th Lane to 91st Avenue
  • Bataan Court from 89th Lane to cul-de-sac
  • Zumbrota Circle from Zumbrota Street to cul-de-sac

Project Status as of 6/9/2023

The project consists of four project areas, which can be seen on the project phasing map. Project newsletters were mailed out on Friday, May 19.

Project Area 1

Construction is anticipated to begin the week of July 31.

Project Area 2

Construction is anticipated to begin the week of June 26.

Project Area 3

Construction is anticipated to begin the week of June 26.

Project Area 4

Construction is anticipated to begin the week of June 26.

For more information, visit BlaineMN.gov/23-08.

Contact Us

This information has been shared with you by the City of Blaine engineering department.

Engineering Department
lgray@blainemn.gov
763-785-6172

Visit us on the web at BlaineMN.gov/Engineering.

Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 City of Blaine. All Rights Reserved.
10801 Town Square Drive NE, Blaine MN 55449

Powered by
CivicSend - A product of CivicPlus