22-04: 2022 Street Reconstructions
Location
- Project Area 1: (123rd Avenue / Buchanan Area)
123rd Avenue from Buchanan Street to Ulysses Street
124th Court from West cul-de-sac to Buchanan Street
124th Court from Pierce Street to Buchanan Street
Pierce Street from West cul-de-sac to Pierce Street
124th Lane from 123rd Avenue to 124th Lane
Pierce Court from Pierce Street to east cul-de-sac
Buchanan Street from Paul Parkway to 124th Lane
- Project Area 2: (127th Avenue / Buchanan Area)
126th Avenue from Polk Street to Taylor Street
126th Lane from Taylor Street to Buchanan Street
127th Avenue from Taylor Street to Buchanan Street
127th Lane from Taylor Street to Central Avenue
Polk Street from 125th Avenue to 126th Avenue
Taylor Street from 126th Avenue to 129th Avenue
Buchanan Street from 126th Avenue to 127th Lane
- Project Area 3: (129th Avenue)
129th Avenue from 180 feet West of Isanti Street to Radisson Road
Project Status as of 8/12/2022
The project consists of three separate project areas, which can be seen on the
22-04 Project Area Map.
Project Area 1During the week of August 15 the contractor will continue restoring any impacted areas behind the curb, with sod scheduled to be installed at the beginning of the week. The final lift of bituminous pavement will be installed in the next couple of weeks once restoration activities are completed.
Project Area 2Construction activities during the week of August 15th will include:
- Removal of any remaining existing concrete curb and gutter
- Partial driveway removals (typically 10 to 15 feet from behind back of curb)
- Installation of concrete curb and gutter on Buchanan Street, Polk Street, 126th Lane, 127th Avenue, and 127th Lane
- Hydrant replacements on 127th Lane
Project Area 3Construction is anticipated to begin the week of September 6 for Project Area 3.
If you have any questions regarding the project, please contact SEH inspector Erk Navratil at 612-257-4184 or
enavratil@sehinc.com.