BlaineMN.gov - Construction Update

Welcome to the Blaine Construction Update

The construction update is published during the construction season and includes details about current road construction projects happening in the City of Blaine. You can subscribe to email notifications by visiting the notify me page and selecting Blaine Construction Update.


22-04: 2022 Street Reconstructions


Location

  • Project Area 1: (123rd Avenue / Buchanan Area)

    123rd Avenue from Buchanan Street to Ulysses Street
    124th Court from West cul-de-sac to Buchanan Street
    124th Court from Pierce Street to Buchanan Street
    Pierce Street from West cul-de-sac to Pierce Street
    124th Lane from 123rd Avenue to 124th Lane
    Pierce Court from Pierce Street to east cul-de-sac
    Buchanan Street from Paul Parkway to 124th Lane

  • Project Area 2: (127th Avenue / Buchanan Area)

    126th Avenue from Polk Street to Taylor Street
    126th Lane from Taylor Street to Buchanan Street
    127th Avenue from Taylor Street to Buchanan Street
    127th Lane from Taylor Street to Central Avenue
    Polk Street from 125th Avenue to 126th Avenue
    Taylor Street from 126th Avenue to 129th Avenue
    Buchanan Street from 126th Avenue to 127th Lane

  • Project Area 3: (129th Avenue)

    129th Avenue from 180 feet West of Isanti Street to Radisson Road

Project Status as of 8/12/2022


The project consists of three separate project areas, which can be seen on the 22-04 Project Area Map.

Project Area 1

During the week of August 15 the contractor will continue restoring any impacted areas behind the curb, with sod scheduled to be installed at the beginning of the week. The final lift of bituminous pavement will be installed in the next couple of weeks once restoration activities are completed.

Project Area 2

Construction activities during the week of August 15th will include:
  • Removal of any remaining existing concrete curb and gutter
  • Partial driveway removals (typically 10 to 15 feet from behind back of curb)
  • Installation of concrete curb and gutter on Buchanan Street, Polk Street, 126th Lane, 127th Avenue, and 127th Lane 
  • Hydrant replacements on 127th Lane

Project Area 3

Construction is anticipated to begin the week of September 6 for Project Area 3.

If you have any questions regarding the project, please contact SEH inspector Erk Navratil at 612-257-4184 or enavratil@sehinc.com.

For additional project information, visit BlaineMN.gov/22-04.

22-05: 89th Avenue and Davenport Area Street Reconstructions


Location

  • Baltimore Street from 85th Avenue to 89th Avenue
  • Davenport Street from 85th Avenue to 89th Avenue
  • 89th Avenue from Central Avenue (MN-65) to Davenport Street
  • 87th Avenue from Central Avenue (MN-65) to Hastings Street
  • Eldorado Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 87th Avenue to northerly dead end
  • Jenkins Court from 85th Avenue to the cul de sac

Project Status as of 8/12/2022


Construction is tentatively scheduled to begin the week of August 22 for the first phases of the project. Due to supply issues, it is anticipated that the project will be constructed over a two year period. Letters will be mailed to residents next week with more information regarding which areas of the neighborhood will be reconstructed this year versus next year.

If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com.

For more information, visit BlaineMN.gov/22-05.




22-06: Hidden Oaks Street Reconstructions


Location

  • 97th Avenue from Hamline Avenue to Yalta Street
  • 97th Lane from Hamline Avenue to Xebec Street
  • 97th Court from West cul-de-sac to Hamline Avenue
  • 98th Avenue from Hamline Avenue to Xebec Street
  • 98th Lane from Wake Street to Yalta Street
  • 99th Avenue from Wake Street to Xebec Street
  • 99th Lane from Xebec Street to Austin Street
  • Hamline Avenue from Edgewood Road to North cul-de-sac
  • Wake Street from 98th Avenue to 99th Avenue
  • Wake Court from 99th Avenue to North cul-de-sac
  • Xebec Street from Edgewood Road to 99th Lane
  • Yalta Street from 97th Avenue to 99th Lane

Project Status as of 8/12/2022


The project will be constructed in two separate phases which can be seen on the Project Phase Map.

Phase 1

Construction activities during the week of August 15 will include:
  • Street grading
  • Installation of the first lift of bituminous pavement (scheduled for August 18 and 19)
  • Boulevard grading
Phase 2

Construction activities during the week of August 15 will include:
  • Removal of any remaining existing concrete curb and gutter
  • Partial driveway removals (typically 10 to 15 feet from behind back of curb)
  • Street grading

If you have any questions regarding the project, please contact WSB inspector Sam Gonsior at 651-380-3272 or sgonsior@wsbeng.com.

For more information, visit BlaineMN.gov/22-06.

Contact Us

This information has been shared with you by the City of Blaine engineering department.

Engineering Department
lgray@blainemn.gov
763-785-6172

Visit us on the web at BlaineMN.gov/Engineering.
Share on Facebook
Share on Twitter
Share via Email

Copyright 2022 City of Blaine. All Rights Reserved.
10801 Town Square Drive NE, Blaine MN 55449

Powered by
CivicSend - A product of CivicPlus