BlaineMN.gov - Construction Update

Welcome to the Blaine Construction Update

The construction update is published during the construction season and includes details about current road construction projects happening in the City of Blaine. You can subscribe to email notifications by visiting the notify me page and selecting Blaine Construction Update.


22-04: 2022 Street Reconstructions


Location

  • Project Area 1: (123rd Avenue / Buchanan Area)

    123rd Avenue from Buchanan Street to Ulysses Street
    124th Court from West cul-de-sac to Buchanan Street
    124th Court from Pierce Street to Buchanan Street
    Pierce Street from West cul-de-sac to Pierce Street
    124th Lane from 123rd Avenue to 124th Lane
    Pierce Court from Pierce Street to east cul-de-sac
    Buchanan Street from Paul Parkway to 124th Lane

  • Project Area 2: (127th Avenue / Buchanan Area)

    126th Avenue from Polk Street to Taylor Street
    126th Lane from Taylor Street to Buchanan Street
    127th Avenue from Taylor Street to Buchanan Street
    127th Lane from Taylor Street to Central Avenue
    Polk Street from 125th Avenue to 126th Avenue
    Taylor Street from 126th Avenue to 129th Avenue
    Buchanan Street from 126th Avenue to 127th Lane

  • Project Area 3: (129th Avenue)

    129th Avenue from 180 feet West of Isanti Street to Radisson Road

Project Status as of 9/9/2022


The project consists of three separate project areas, which can be seen on the 22-04 Project Area Map.

Project Area 1

The contractor has completed restoration within the project area. The final lift of bituminous pavement will be installed during the week of September 12.

Project Area 2

Construction activities during the week of September 12 will include:
  • Paving bituminous driveways
  • Irrigation system repairs
  • Boulevard grading and restoration 
 Project Area 3

Westbound 129th Avenue will be closed starting Tuesday, September 13 from approximately 200 feet west of Isanti Street to Radisson Road (see detour map at BlaineMN.gov/22-04). Construction during the week of September 12 will include:
  • Reclaiming of the existing bituminous pavement
  • Removal of the existing concrete curb and gutter
  • Partial driveway removals
If you have any questions regarding the project, please contact SEH inspector Erk Navratil at 612-257-4184 or enavratil@sehinc.com.

For additional project information, visit BlaineMN.gov/22-04.

22-05: 89th Avenue and Davenport Area Street Reconstructions


Location

  • Baltimore Street from 85th Avenue to 89th Avenue
  • Davenport Street from 85th Avenue to 89th Avenue
  • 89th Avenue from Central Avenue (MN-65) to Davenport Street
  • 87th Avenue from Central Avenue (MN-65) to Hastings Street
  • Eldorado Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 87th Avenue to northerly dead end
  • Jenkins Court from 85th Avenue to the cul de sac

Project Status as of 9/9/2022


The project consists of 5 phases, which can be seen on the project phasing map below. Phases 1-3 are anticipated to be completed this year, with phases 4-5 being constructed in 2023 (it is possible that portions of phase 2 are not constructed until 2023). The completion date for all work taking place in 2022 is November 4.

Phase 1

Construction activities during the week of September 12 will include:
  • Storm sewer installation
  • Hydrant replacements
  • Partial driveway removals (typically 10 to 15 feet from behind back of curb)
  • Street grading
Phase 2

Construction is likely to begin in Spring of 2023. More information will be mailed to these residents in the coming weeks.

Phase 3

Construction is anticipated to begin the week of September 19.

Phases 4-5

Construction will begin in Spring of 2023. More information will be mailed to these residents in the coming weeks.

If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com.

For more information, visit BlaineMN.gov/22-05.




22-06: Hidden Oaks Street Reconstructions


Location

  • 97th Avenue from Hamline Avenue to Yalta Street
  • 97th Lane from Hamline Avenue to Xebec Street
  • 97th Court from West cul-de-sac to Hamline Avenue
  • 98th Avenue from Hamline Avenue to Xebec Street
  • 98th Lane from Wake Street to Yalta Street
  • 99th Avenue from Wake Street to Xebec Street
  • 99th Lane from Xebec Street to Austin Street
  • Hamline Avenue from Edgewood Road to North cul-de-sac
  • Wake Street from 98th Avenue to 99th Avenue
  • Wake Court from 99th Avenue to North cul-de-sac
  • Xebec Street from Edgewood Road to 99th Lane
  • Yalta Street from 97th Avenue to 99th Lane

Project Status as of 9/9/2022


The project consists of two phases, which can be seen on the Project Phase Map.

Phase 1

Construction activities during the week of September 12 will include:
  • Irrigation system repairs
  • Boulevard grading and restoration
  • Permanent mailbox installation
Phase 2

Construction activities during the week of September 12 will include:
  • Street grading
  • Installation of the first lift of bituminous pavement (scheduled for September 14)
The final lift of bituminous pavement for both phases is scheduled for the week of October 17.

If you have any questions regarding the project, please contact WSB inspector Sam Gonsior at 651-380-3272 or sgonsior@wsbeng.com.

For more information, visit BlaineMN.gov/22-06.

Contact Us

This information has been shared with you by the City of Blaine engineering department.

Engineering Department
lgray@blainemn.gov
763-785-6172

Visit us on the web at BlaineMN.gov/Engineering.
Share on Facebook
Share on Twitter
Share via Email

Copyright 2022 City of Blaine. All Rights Reserved.
10801 Town Square Drive NE, Blaine MN 55449

Powered by
CivicSend - A product of CivicPlus