22-04: 2022 Street Reconstructions
Location
- Project Area 1: (123rd Avenue / Buchanan Area)
123rd Avenue from Buchanan Street to Ulysses Street
124th Court from West cul-de-sac to Buchanan Street
124th Court from Pierce Street to Buchanan Street
Pierce Street from West cul-de-sac to Pierce Street
124th Lane from 123rd Avenue to 124th Lane
Pierce Court from Pierce Street to east cul-de-sac
Buchanan Street from Paul Parkway to 124th Lane
- Project Area 2: (127th Avenue / Buchanan Area)
126th Avenue from Polk Street to Taylor Street
126th Lane from Taylor Street to Buchanan Street
127th Avenue from Taylor Street to Buchanan Street
127th Lane from Taylor Street to Central Avenue
Polk Street from 125th Avenue to 126th Avenue
Taylor Street from 126th Avenue to 129th Avenue
Buchanan Street from 126th Avenue to 127th Lane
- Project Area 3: (129th Avenue)
129th Avenue from 180 feet West of Isanti Street to Radisson Road
Project Status as of 9/16/2022
The project consists of three separate project areas, which can be seen on the
22-04 Project Area Map.
Project Area 1The contractor has completed restoration within the project area. The final lift of bituminous pavement will be installed during the week of September 19.
Project Area 2Construction activities during the week of September 19 will include:
- Irrigation system repairs
- Boulevard grading and restoration
Project Area 3129th Avenue is currently closed from approximately 200 feet west of Isanti Street to Radisson Road (see detour map below). Construction during the week of September 19 will include:
- Removal of the existing concrete curb and gutter
- Partial driveway removals
- Storm sewer installation
- Hydrant replacements
If you have any questions regarding the project, please contact SEH inspector Erk Navratil at 612-257-4184 or