21-30: Lift Station 13 Force Main Replacement Project - Phase 1


Location

West 35W Service Drive from 93rd Avenue to 95th Avenue.  Green space area between 95th Avenue and Naples Street.

Project Status as of 9/15/2023

The project location can be seen on the 21-30 Location Map.

Starting on September 18, West 35W Frontage Road will be closed from 93rd Avenue to 95th Avenue. This road closure is anticipated to last until November 20. Construction activities during the week of September 18 will include:

  • Removal of bituminous pavement and concrete curb and gutter in select areas
  • Private utility relocation
  • Preparation for trenchless sanitary sewer crossing at 95th Avenue

For additional project information, visit BlaineMN.gov/21-30.


22-05: 89th Avenue and Davenport Area Street Reconstructions

Location

  • Baltimore Street from 85th Avenue to 89th Avenue
  • Davenport Street from 85th Avenue to 89th Avenue
  • 89th Avenue from Central Avenue (MN-65) to Davenport Street
  • 87th Avenue from Central Avenue (MN-65) to Hastings Street
  • Eldorado Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 85th Avenue to 87th Avenue
  • Goodhue Street from 87th Avenue to northerly dead end
  • Jenkins Court from 85th Avenue to the cul de sac

Project Status as of 9/15/2023

The project consists of five phases, which can be seen on the project phasing map below. Phase 1 was completed in 2022, with phases 2-5 being constructed in 2023.

Phase 1

Construction completed in 2022.

Phase 2

Construction completed in 2023.

Phase 3

Construction completed in 2023.

Phases 4-5

Construction during the week of September 18 will include:

  • Installation of the first lift of bituminous pavement
  • Installation of the final lift of bituminous pavement on select streets where base pavement was previously installed and boulevard restoration has been completed. 

If you have any questions regarding the project, please contact Bolton & Menk inspector Travis Pearl at 612-599-3191 or travis.pearl@bolton-menk.com.

For more information, visit BlaineMN.gov/22-05.


23-01: 99th Avenue and Baltimore Street Roundabout

Location

99th Avenue and Baltimore Street

Project Status as of 9/15/2023

View the project map for area layout.

The Contractor has finished the subgrade preparation and has installed the gravel layer.  For the week of September 18, the Contractor will be installing curb and gutter and continue work to prepare for paving.

For additional project information, visit BlaineMN.gov/23-01.


23-06: Northwest Area Street Reconstruction

Location

Project Area 1

  • 127th Avenue from cul-de-sac to Polk Street
  • 127th Lane from Monroe Street to Polk Street
  • 128th Avenue from Taylor Street to Polk Street
  • 129th Lane from 175 feet west of Tyler Street to Polk Street
  • Tyler Street from 127th Lane to 129th Lane
  • Polk Street from 126th Avenue to cul-de-sac

Project Area 2

  • 131st Avenue (E) from Van Buren Street to Taylor Street

Project Area 3

  • 131st Avenue (W) from Jefferson Street to Van Buren Street

Project Status as of 9/15/2023

The project consists of two phases, which can be seen on the project phasing map.

Phase 1

Construction activities during the week of September 18 will include:

  • Irrigation system repairs
  • Boulevard grading and restoration

Phase 2

Construction activities during the week of September 18 will include:

  • Irrigation system repairs
  • Boulevard grading and restoration

If you have any questions regarding the project, please contact SEH inspector Erik Navratil at 612-257-4184 or enavratil@sehinc.com.

For more information, visit BlaineMN.gov/23-06.


23-08: Southeast Area Street Reconstruction

Location

Project Area 1

  • 97th Lane from Austin Street to Lexington Avenue
  • 98th Avenue from Austin Street to Cord Street
  • 98th Lane from Austin Street to Cord Street
  • 99th Avenue from Austin Street to Lexington Avenue
  • Austin Street from Edgewood Road to 97th Lane
  • Austin Street from 98th Avenue to Lexington Avenue
  • Cord Street from 98th Avenue to Austin Street
  • Edgewood Road cul-de-sac (4023-4083)
  • Edgewood Road cul-de-sac (4103-4163)

Project Area 2

  • West 35W Service Drive from West 35W Service Drive to cul-de-sac

Project Area 3

  • Edison Street from 85th Avenue to cul-de-sac

Project Area 4

  • 89th Lane from Yancy Street to 90th Lane
  • 89th Court from 90th Lane to cul-de-sac
  • 90th Lane from Zumbrota Street to Rice Creek Parkway
  • Bataan Street from 90th Lane to 91st Avenue
  • Yancy Street from Rice Creek Parkway to 89th Lane
  • Zumbrota Street from 89th Lane to 91st Avenue
  • Bataan Court from 89th Lane to cul-de-sac
  • Zumbrota Circle from Zumbrota Street to cul-de-sac

Project Status as of 9/15/2023

The project consists of four project areas, which can be seen on the project phasing map. Project newsletters were mailed out on Friday, May 19.

Project Area 1

Construction activities during the week of September 18 will include:

  • Boulevard grading and restoration

Project Area 2

Construction has been completed.

Project Area 3

Construction has been completed in project area 3 except for minor punch list items.

Project Area 4

Construction has been completed in project area 4 except for minor punch list items.

If you have any questions regarding the project, please contact WSB inspector Sam Gonsior at 651-380-3272 or sgonsior@wsbeng.com.

For more information, visit BlaineMN.gov/23-08.

Contact Us

This information has been shared with you by the City of Blaine engineering department.

Engineering Department
lgray@blainemn.gov
763-785-6172

Visit us on the web at BlaineMN.gov/Engineering.

Share on Facebook
Share on Twitter
Share via Email

Copyright 2023 City of Blaine. All Rights Reserved.
10801 Town Square Drive NE, Blaine MN 55449

Powered by
CivicSend - A product of CivicPlus